Location/Limits: Tierra Del Sol Park to Ingram Rd
Project Start Date: Q2 2023
Anticipated Completion: Q3 2026
Status: Bid Phase
Budget: $9,507,699
Funding: City of San Antonio Bond
Additional Information:
Design Consultant: None
Contractor: TBD
Status of Bidding: Negotiations
This project continues trail improvements along Zarzamora Creek as part of the Howard W. Peak Greenway Trails System, extending from Ingram Road downstream to Tierra Del Sol Park. Upon completion, it will enhance trail access and connect Zarzamora Creek to the broader Westside Creeks network and the San Antonio River Mission Reach. This linkage will provide continuous, safe hiking and biking routes for residents and visitors, improving access to parks, swimming pools, and other community assets.