- Location: 8561 Rochelle Street, San Antonio, TX
- Project Completion Date: November 2, 2017
- Project Features: 2 Permeable Pavements
- N/A
Project Details:
- Total Impervious Area (SF): 14,810
- Total Target Volume (CF): 1,851
- Total Treatment Percentage (% of Target from 1.5" 24-Hour Storm): 42.1%
- Total Impervious Area to Treatment (SF): 6,232
- Total Annual Volume Treated (CF): 16,383
- Total Bacteria Load Removed (Colonies/yr): 217 billion
- Total Sediment Load Removed (lb/yr): 41