- Location: 6405 El Verde Road, San Antonio, TX
- Project Completion Date: November 2, 2017
- Project Features: 2 Permeable Pavements
- N/A
Project Details:
- Total Impervious Area (SF): 8,500
- Total Target Volume (CF): 1,063
- Total Treatment Percentage (% of Target from 1.5" 24-Hour Storm): 97.7%
- Total Impervious Area to Treatment (SF): 8,304
- Total Annual Volume Treated (CF): 21,844
- Total Bacteria Load Removed (Colonies/yr): 131 billion
- Total Sediment Load Removed (lb/yr): 27