- Location: 6892 W US Highway 90, San Antonio, TX
- Project Completion Date: May 11, 2020
- Project Features: 3 Bioretentions
- N/A
Project Details:
- Total Impervious Area (SF): 48,856
- Total Target Volume (CF): 6,107
- Total Treatment Percentage (% of Target from 1.5" 24-Hour Storm): 156.1
- Total Impervious Area to Treatment (SF): 76,280
- Total Annual Volume Treated (CF): 185,331
- Total Bacteria Load Removed (Colonies/yr): 2,217 billion
- Total Sediment Load Removed (lb/yr): 485
Share: