- Location: 996 S Hackberry, San Antonio, TX
- Project Completion Date: June 5, 2015
- Project Features: 1 Bioretention, 1 Cistern
- N/A
Project Details:
- Total Impervious Area (SF): 124,571
- Total Target Volume (CF): 15,571
- Total Treatment Percentage (% of Target from 1.5" 24-Hour Storm): 8.0%
- Total Impervious Area to Treatment (SF): 16,788
- Total Annual Volume Treated (CF): 32,665
- Total Bacteria Load Removed (Colonies/yr): 393 billion
- Total Sediment Load Removed (lb/yr): 81